You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 15 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days. Question: Do you expect to receive a bonus or penalty? How much do you expect to be given a bonus or penalty?

+2
Answers (1)
  1. 16 February, 05:10
    0
    A) I expect to receive a bonus

    B) I expect to get a $500 bonus by finishing within 15 working days.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 15 working ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.