Cosi Company uses a job order costing system and allocates its overhead on the basis of direct labor costs. Cosi expects to incur $830,000 of overhead during the next period, and expects to use 53,000 labor hours at a cost of $10.00 per hour. What is Cosi Company's predetermined overhead rate?

+4
Answers (1)
  1. 2 October, 06:56
    0
    156.6%

    Explanation:

    Given:

    Cosi Company's Incurred over head for the next period = $830,000

    Expected labor hours = 53,000

    Cost of labor = $10.00 per hour

    Thus,

    Total labor cost = 53,000 * $10.00 = $530,000

    Now,

    the Cosi Company's predetermined overhead rate will be calculated as:

    Predetermined overhead rate = Incurred overhead / Total labor cost

    on substituting the respective values, we get

    Predetermined overhead rate = ($830,000 / 530,000) = 1.566

    or

    Predetermined overhead rate = 1.566 * 100% = 156.6%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Cosi Company uses a job order costing system and allocates its overhead on the basis of direct labor costs. Cosi expects to incur $830,000 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.