A On December 31, 2017, State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to manufacture a bridge over the New River. State Construction anticipates the construction will take three years. The company's accountants provide the following contract details relating to the project: Contract price $780 million Estimated construction costs $600 million Estimated total profit $180 million During the three-year construction period, State Construction incurred costs as follows: 2018 $ 60 million 2019 $360 million 2020 $180 million State Construction uses the cost-to-cost method to recognize revenue. Calculate the revenue recognized in 2018, 2019, and 2020.

+4
Answers (1)
  1. 25 June, 06:27
    0
    2018: $78 million

    2019: $468 million

    2020: $234 million

    Explanation:

    Given that State Construction incurred costs as follows:

    Year Cost

    2018 $60 million

    2019 $360 million

    2020 $180 million

    Total cost = $60 million + $360 million + $180 million = $600 million

    Percentage to total cost ratio is:

    For 2018 = $60 million / $600 million = 0.1,

    For 2019 = $360 million / $600 million = 0.6,

    For 2020 = $180 million / $600 million = 0.3.

    Revenue = Percentage to total cost ratio * Contract price.

    Contract price = $780 million

    For 2018, Revenue = 0.1 * $780 million = $78 million

    For 2019, Revenue = 0.6 * $780 million = $468 million

    For 2020, Revenue = 0.3 * $780 million = $234 million
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A On December 31, 2017, State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.