e following information pertains to Sigma Company for September: Direct Material Direct Labor Overhead Job #323 $3,200 $4,500? Job #325? 5,000? Job #401 5,670? $5,550 Sigma Company applies overhead for Job #323 at 140 percent of direct labor cost and at 150 percent of direct labor cost for Jobs #325 and #401. The total cost of Jobs #323 and #325 is identical. Refer to Sigma Co. What amount of overhead is applied to Job #323?

+5
Answers (1)
  1. 30 January, 16:22
    0
    The amount of Overhead applied to

    Job # 323 is $ 6300

    Explanation:

    Direct Material Direct Labor Overhead

    Job #323 $3,200 $4,500? (applies overhead for Job #323 at 140 percent of direct labor cost)

    Job #325? 5,000? (150 percent of direct labor cost for Jobs #325)

    Job #401 5,670? $5,550 (150 percent of direct labor cost for Jobs #401)

    We can easily calculate the missing values by using the information given

    The amount of Overhead applied to

    Job # 323 is 140 % of $ 4500

    $ 4500 * 140% = $ 6300

    Job # 325 is 150 % of $ 5000

    $ 5000 * 150% = $ 7500

    The total Cost of

    Job # 323 = $3200 + $ 4500 + $ 6300 = $ 14000

    Job # 325 = $ 1500 + $ 5000 + $ 7500 = $ 14000

    Materials Job # 325 = $ 1500

    Job #401

    Direct labor = FOH / 150% = $5550/150% = $ 3700
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “e following information pertains to Sigma Company for September: Direct Material Direct Labor Overhead Job #323 $3,200 $4,500? Job #325? ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.