Ask Question
4 February, 11:10

Piper Corporation's standards call for 3,900 direct labor-hours to produce 1,300 units of product. During October the company worked 1,200 direct labor-hours and produced 1,200 units. The standard hours allowed for October would be:

a. 3,900 hours

b. 1,200 hours

c. 3,600 hours

d. 2,700 hours

+1
Answers (1)
  1. 4 February, 12:37
    0
    The correct answer is C.

    Explanation:

    Giving the following information:

    Piper Corporation's standards call for 3,900 direct labor-hours to produce 1,300 units of product. During October the company worked 1,200 direct labor-hours and produced 1,200 units.

    The standard hour allowed is the number of hours that takes to produce a certain number of units.

    First, we need to determine the standard hours per unit:

    Standard hour per unit = 3,900/1,300 = 3 hours per unit

    Now, for 1,200 units:

    Standard hours allowed = 1,200*3 = 3,600 hours
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Piper Corporation's standards call for 3,900 direct labor-hours to produce 1,300 units of product. During October the company worked 1,200 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers