A company makes concrete statues. Each statue requires 10 pounds of concrete at $2 per pound and 0.2 direct labor hours at $30 per hour. Overhead is assigned at the rate of $80 per labor hour. What is the standard cost to make one unit and the total that would appear on the standard cost card?

+4
Answers (1)
  1. 8 September, 13:31
    0
    the standard cost to make one unit is $42

    Explanation:

    Standard Costing is the Cost established from the firm's Past experience.

    Standard Costing Calculation for Concrete statues

    Material

    Concrete (10 pounds*$2) $20

    Labor

    Direct Labor (0.2 direct labor hours * $30) $6

    Overheads

    Allocated ($80*0.2 direct labor hours) $16

    Total $42
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A company makes concrete statues. Each statue requires 10 pounds of concrete at $2 per pound and 0.2 direct labor hours at $30 per hour. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.