A project cpm has a critical path of bdeg. activity e is assumed to be 6 days. your analysis suggests that there is a 10% probability that activity e will take 4 days, a 50% probability e will take 5 days, a 30% probability activity e will take 6 days, and a 10% probability activity e will take 7 days. what is the expected effect on the project duration?

+4
Answers (1)
  1. 7 April, 19:51
    0
    Check answer from google and report to teacher
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A project cpm has a critical path of bdeg. activity e is assumed to be 6 days. your analysis suggests that there is a 10% probability that ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.