Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $36 million. Construction costs incurred in the first year were $26 million and estimated remaining costs to complete at the end of the year were $18 million.

How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion method?

+2
Answers (1)
  1. 6 December, 19:51
    0
    Loss of $4.76 will be recognized.

    Explanation:

    Percentage of completion = 26 / (26+18) = 59%

    Contract price=$36*59%=$21.24

    Loss recognized=Revenue-Costs incurred=$21.24-$26 = ($4.76) million
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $36 million. Construction costs incurred ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers