A construction company entered into a fixed-price contract to build an office building for $16 million. Construction costs incurred during the first year were $3 million and estimated costs to complete at the end of the year were $7 million. During the first year the company billed its customer $3 million, of which $1 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method

+2
Answers (1)
  1. 14 August, 00:38
    0
    On the balance sheet it will appear:

    account receivable 2,000,000

    unbilled contract revenue 1,800,000

    Explanation:

    Using percentage of completion method:

    3,000,000 cost incurred + 7,000,000 cost to complete = 10,000,000 total cost

    3,000,000/10,000,000 = 30%

    16,000,000 revenue x 30% = 4,800,000 millions

    cash 1,000,000

    account receivable 2,000,000

    unbilled contract receivable 1,800,000

    contract revenue earned 4,800,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A construction company entered into a fixed-price contract to build an office building for $16 million. Construction costs incurred during ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.