Ask Question
27 April, 10:33

An automated machine fills bottles with a mean of 16 oz. and standard deviation of 0.1 oz. Assuming that Cpk index is 1 for this process, what are the lower and upper specification limits? Multiple Choice 1. lower spec = 14.3 ounces and upper spec = 17.7 ounces 2. There is insufficient information to determine the process specification. 3. lower spec = 15.7 ounces and upper spec = 16.3 ounces 4. lower spec = 12.0 ounces and upper spec = 21.4 ounces 5. lower spec = 0.1 ounces and upper spec = 1 ounce

+4
Answers (1)
  1. 27 April, 13:37
    0
    The correct answer is option 2.

    There is insufficient information to determine the process specification.

    Explanation:

    There is insufficient information to determine the process specification

    CpK = Min (CpU, CpL)

    CpU = (Upper Specification Limit - Mean) / 3*Standard Deviation

    CpL = (Mean - Lower Specification Limit) / 3*Standard Deviation

    Hence, as both upper Specification Limit and lower specification limit is not mentioned, it cannot be measured.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “An automated machine fills bottles with a mean of 16 oz. and standard deviation of 0.1 oz. Assuming that Cpk index is 1 for this process, ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.