Labor Variances Verde Company produces wheels for bicycles. During the year, 660,000 wheels were produced. The actual labor used was 360,000 hours at $9.50 per hour. Verde has the following labor standards: 1) $10.00 per hour; 2) 0.5 hour per wheel.

+4
Answers (1)
  1. 3 March, 09:14
    0
    Answer and Explanation:

    Given:

    Actual output = 660,000

    Actual labor hours = 360,000 at $9.50 per hour

    Standard labor rate = $10 per hour

    Standard output hour = 0.5 hour per wheel

    Computation:

    Labor Variances includes:

    1. Labor Cost Variance

    2. Labor Rate Variance

    3. Labor Efficiency Variance

    1. Labor Cost Variance = (SR*SH) - (AR*AH)

    Labor Cost Variance = [$10 (Actual output*Standard output hour) ] - [$9.5*360000]

    Labor Cost Variance = [$10*330,000] - $3,420,000

    Labor Cost Variance = $120,000 (Adverse)

    2. Labor Rate Variance = (SR-AR) AH

    Labor Rate Variance = ($10-$9.5) * 360,000

    Labor Rate Variance = $180,000 (Favorable)

    3. Labor Efficiency Variance = (SH - AH) * SR

    Labor Efficiency Variance = [ (Actual output*Standard output hour) - 360,000]*10

    Labor Efficiency Variance = (330,000 - 360,000) * 10

    Labor Efficiency Variance = $300,000 (Adverse)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Labor Variances Verde Company produces wheels for bicycles. During the year, 660,000 wheels were produced. The actual labor used was ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.