A process currently services an average of 50 custom-ers per day. Observations in recent weeks show that its utilization is about 90 percent, allowing for just a 10 percent capacity cushion. If demand is expected to be 75 percent of the current level in five years and management wants to have a capacity cushion of just 5 percent, what capacity requirement should be planned?

+3
Answers (1)
  1. 11 November, 11:25
    0
    40 customers

    Explanation:

    Expected Demand Rate*current service rate/current utilization=capacity requirement/required utilization

    .75 * (50/90) = x/.95

    x=39.58

    x=40 customers
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A process currently services an average of 50 custom-ers per day. Observations in recent weeks show that its utilization is about 90 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers