Livermore Industries uses a kanban system to manage production of the KR-9 subassembly. In a ten-hour day, they use 1500 units and use containers that can hold 50 units each. It takes 45 minutes to fill and move a container of parts to the right place on the KR-9 line that is currently rated at a 15% safety factor. How many production cards are needed

+1
Answers (1)
  1. 10 November, 15:42
    0
    3 cards are required since given problem statement states that 15% as safety factor.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Livermore Industries uses a kanban system to manage production of the KR-9 subassembly. In a ten-hour day, they use 1500 units and use ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.