If your company needs to produce 7,800 products by the end of the next 12 weeks, how many products will you need to produce each week to finish on schedule?

A. 680

B. 650

C. 620

D. 580

+2
Answers (2)
  1. 3 August, 01:27
    0
    B. 650

    7800 divided among 12 weeks is 650.
  2. 3 August, 02:18
    0
    B. 650

    Divide number of units by number of weeks

    7800 units/12 weeks = 650 units per week on average
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If your company needs to produce 7,800 products by the end of the next 12 weeks, how many products will you need to produce each week to ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.