Sarasota company manufactures pillows in the cutting and assembly process. pillows are manufactured in 40-pillow batch sizes. the cutting time is 4 minutes per pillow. the assembly time is 8 minutes per pillow. it takes 10 minutes to move a batch of pillows from cutting to assembly. what is the value-added lead time?

a. 10 minutes

b. 22 minutes

c. 12 minutes

d. 8 minutes

+3
Answers (1)
  1. 13 August, 22:37
    0
    Answer: c. 12 minutes

    Value added time is the amount of time it takes to actually produce and improve a product. In the case of Sarasota company who manufactures pillows, value added time is the production time which is 4 minutes in cutting and 8 minutes in the assembly, total of 12 minutes.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Sarasota company manufactures pillows in the cutting and assembly process. pillows are manufactured in 40-pillow batch sizes. the cutting ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers