Misleading cost numbers are larger when unit-level assignments and the alternative activity-cost-driver assignments are proportionatley similar to each other.

True / False.

+3
Answers (1)
  1. 18 February, 05:28
    0
    The correct answer is False.

    Explanation:

    Misleading cost numbers are considered to be higher when their unit allocations and the alternative activity-cost-driver allocations are proportionally different from each other. This means that it corresponds to the contrary to what is detailed in the statement.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Misleading cost numbers are larger when unit-level assignments and the alternative activity-cost-driver assignments are proportionatley ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.