Qs 20-13 manufacturing: direct materials budget lo p1 miami solar manufactures solar panels for industrial use. the company budgets production of 5,000 units (solar panels) in july and 5,300 units in august. each unit requires 3 pounds of direct materials, which cost $6 per pound. the companyâs policy is to maintain direct materials inventory equal to 30% of the next monthâs direct materials requirement. as of june 30, the company has 4,500 pounds of direct materials in inventory, which complies with the policy. prepare a direct materials budget for july.

+5
Answers (1)
  1. 1 June, 14:32
    0
    Calculation of Direct Material Budget for the month of July:

    Budgeted production (Units) for July 5,000

    Material required per unit (pounds) 3

    Material requirement for July (pounds) = (5000 units * 3 pounds) 15,000

    Add: Ending material inventory (5300 units * 3 pounds * 30%) 4,770

    Less: Beginning material inventory 4,500

    Direct Material Purchase (Pounds) (15000+4770-4500) = 15,270

    Cost per pound of Metrial ($) $6.00

    Direct Material Purchase ($) (15270 pounds * $6) = $91,620
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Qs 20-13 manufacturing: direct materials budget lo p1 miami solar manufactures solar panels for industrial use. the company budgets ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.