A standard differs from a budget because a standard is a unit amount. none of these; a standard does not differ from a budget. is a predetermined cost. contributes to management planning and control.

+1
Answers (1)
  1. 2 June, 16:48
    0
    Standard cost is the amount management thinks should be incurred to produce a good or service. A standard differs from a budget because a standard is a unit amount. A budget on the other hand expresses a total amount. Using standard costs provides a basis for evaluating cost control.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A standard differs from a budget because a standard is a unit amount. none of these; a standard does not differ from a budget. is a ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.