Ask Question
10 August, 01:45

A production line is to be designed to make 500 El-More dolls per day. Each doll requires 11 activities totaling 16 minutes of work. The factory operates 1000 minutes per day. What is the required cycle time for this assembly line?

a. one-half minute.

b. one and one-half minutes.

c. two minutes.

d. 5,500 minutes.

+3
Answers (2)
  1. 10 August, 02:34
    0
    The required cycle time for this assembly line is 2 minutes.

    Explanation: Given that

    The factory operates for 1000 minutes/day

    Daily operating time = factory operates 1000 minutes per day

    Schedule output = 500 El

    Hence, to calculate the required cycle time for the assembly line

    Cycle time = daily operating time : the output schedule.

    1000 / 500 = 2 minutes
  2. 10 August, 03:51
    0
    The required cycle time for this assembly line is 2 minutes. The rigtht answer is c.

    Explanation:

    Acording to the data, we have the following:

    Daily operating time = factory operates 1000 minutes per day

    Scheduled output=make 500 El-More dolls per day

    Therefore, to calculate the required cycle time for this assembly line we have to use the following formula:

    Cycle time = daily operating time divided by the scheduled output

    = 1000 / 500 = 2 minutes

    The required cycle time for this assembly line is 2 minutes.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A production line is to be designed to make 500 El-More dolls per day. Each doll requires 11 activities totaling 16 minutes of work. The ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers