E. Used for comparing alternative projects or designs
F. Used for project control
G. Quick and has high margin of error
H. Used for making initial financial arrangements
I. Its concept depends on comparing the unit cost to
similar previous projects
J. Its concept depends on actual quantities and estimated
prices for the estimated project
+1
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Check the right boxes in the table below: Statement Approximate Detailed Estimates Estimates A. Requires completed design documents B. Used ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.