Many project managers like to use the Tracking table to update progress because it shows the currently scheduled task start and finish dates (the Update Tasks dialog box does not show the scheduled start and finish dates). A. TrueB. False

+2
Answers (1)
  1. 4 May, 06:34
    0
    False

    Explanation:

    It is incorrect
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Many project managers like to use the Tracking table to update progress because it shows the currently scheduled task start and finish ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.