Condor Airplane Company has built a new model jet aircraft which it intends to sell to high net worth clients. This aircraft required 25,000 hours to complete. Condor believes an incremental unit-time learning model with an 82% learning curve best reflects the company's production efficiency. Condor just received a contract to make fifteen identical aircraft. What will be the expected unit time for the sixteenth aircraft?

+5
Answers (1)
  1. 21 August, 14:15
    0
    11,303 Hrs

    Explanation:

    Now here, we can use the learning curve formula, which is as under:

    Y = a * X^ (log of learning rate / log 2)

    Here

    Y is the average time taken by each unit

    a is the time taken by the first unit which is 25000 hrs

    X is the number of units to be produced which is 16 unit (Including the first unit)

    Learning Rate is given and is 82%

    So by putting values we have:

    Y = 25,000 hrs * 16 ^ (Log 0.82 / Log 2)

    Y = 25,000 * 16^ (-0.2863)

    Y = 25,000 * 0.45212 = 11,303 Hrs
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Condor Airplane Company has built a new model jet aircraft which it intends to sell to high net worth clients. This aircraft required ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers