The following information was collected on work Center 40: 400 hours scheduled; 30 hours lost due to absenteeism; 20 hours lost while waiting for tooling; 40 hours lost due to power failure; and 300 standard hours of production achieved. Calculate the work center utilization.

+3
Answers (1)
  1. 2 December, 20:49
    0
    75% is the work center utilization

    Explanation:

    Mathematically;

    Utilization = (Actual Output/Design capacity) * 100

    From the question;

    Actual output = 300

    Design capacity = 400

    Substituting these values in the equation, we have:

    = (300/400) * 100

    = 0.75*100

    = 75%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The following information was collected on work Center 40: 400 hours scheduled; 30 hours lost due to absenteeism; 20 hours lost while ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers