MC Qu. 95 A job was budgeted to require ... A job was budgeted to require 2 hours of labor per unit at $12.00 per hour. The job consisted of 8,000 units and was completed in 15,000 hours at a total labor cost of $196,200. What is the direct labor rate variance?

+1
Answers (1)
  1. 11 August, 23:39
    0
    The direct labor rate variance is negative 16,500

    Explanation:

    8,000 units at 2hours per unit = 16,000 hours x $12 per hour = $192,000 standart cost for the job

    actual 15,000 hours and $196,200 total labor cost

    labor cost per hour = 196,200/15,000 = 13.1 actual rate per hour

    (standar rate - actual rate) x actual hours = rate variance

    (12 - 13.1) x 15,000 = - 1.1 x 15,000 = - 16,500
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “MC Qu. 95 A job was budgeted to require ... A job was budgeted to require 2 hours of labor per unit at $12.00 per hour. The job consisted ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.