The budgeted production of Taurus, Inc. is 13,000 units per month. Each unit requires 30 minutes of direct labor to complete. The direct labor rate is $80 per hour. Calculate the budgeted cost of direct labor for the month. (Round any intermediate calculations to the nearest cent and your final answer to the nearest dollar.)

+1
Answers (1)
  1. 9 July, 19:48
    0
    Direct labor cost = $520,000

    Explanation:

    Giving the following information:

    The budgeted production of Taurus, Inc. is 13,000 units per month. Each unit requires 30 minutes of direct labor to complete. The direct labor rate is $80 per hour.

    First, we need to calculate the total direct labor hours:

    Direct labor hours = 13,000*0.5 = 6,500 hours

    Now, we can calculate the direct labor cost:

    Direct labor cost = 6,500*80 = $520,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The budgeted production of Taurus, Inc. is 13,000 units per month. Each unit requires 30 minutes of direct labor to complete. The direct ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.