Extreme Builders constructs houses. The standard labor rate is $25 per hour and the standard number of hours is 15,000 hours per home. During the year, it constructed 12 homes using 18,000 labor hours per home and a rate of $28 per hour. Calculate the Extreme Builders' labor rate variance. a.$648,000 F b.$540,000 F c.$648,000 U d.$540,000 U

+4
Answers (1)
  1. 24 March, 18:55
    0
    Direct labor rate variance = $648,000 unfavorable

    Explanation:

    Giving the following information:

    The standard labor rate is $25 per hour. During the year, it constructed 12 homes using 18,000 labor hours per home and a rate of $28 per hour.

    To calculate the direct labor rate variance, we need to use the following formula:

    Direct labor rate variance = (Standard Rate - Actual Rate) * Actual Quantity

    Direct labor rate variance = (25 - 28) * 216,000

    Direct labor rate variance = $648,000 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Extreme Builders constructs houses. The standard labor rate is $25 per hour and the standard number of hours is 15,000 hours per home. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.