Put the Procurement to Payment process steps in order of occurence: 1. Vendor Payment 2. Create and send Purchase Order to vendor 3. Create purchase requisition 4. Vendor Selection 5. Shipment ot item ordered from vendor 6. Invoice receipt 7. Goods Receipt

+4
Answers (1)
  1. 7 May, 22:55
    0
    The correct sequence is as follows;

    3. Create purchase requisition - 4. Vendor Selection - 2. Create and send Purchase Order to vendor - 5. Shipment of item ordered from vendor - 7. Goods Receipt - 6. Invoice receipt - 1. Vendor Payment

    Explanation:

    In making a requisition, the first step is to create the purchase requisition. This then drives or informs the selection of a vendor.

    Then, the purchase order is created and sent to the vendor. The vendor ships based on the purchase order, the goods are received and acknowledged.

    The seller sends the invoice which informs the amount to be paid.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Put the Procurement to Payment process steps in order of occurence: 1. Vendor Payment 2. Create and send Purchase Order to vendor 3. Create ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.