A process currently services an average of 43 customers per day. Observations in recent weeks show that its utilization is about 90 percent, allowing for just a 10 percent capacity cushion. If demand is expected to be 70 percent of the current level in five years and management wants to have a capacity cushion of just 8 percent, what capacity requirement should be planned?

+3
Answers (1)
  1. 12 January, 05:47
    0
    The correct answer is 31 customers per day.

    Explanation:

    Consider the current capacity requirement as = x

    Management wants to have a capacity cushion = 8%.

    So the utilization is required = 100% - 8% = 92%

    A process of currently services an average of 43 customers per day and utilization is 90%.

    Expected Demand=70% = 70 : 100 = 0.70

    Current utilization = 90% = 0.90

    Let Capacity requirement = X

    Capacity requirement : required utilization = Expected Demand rate * current service rate : current utilization rate

    X : 0.92 = 0.70 * 43 : 0.90

    X = 0.70 * 43 : 0.90 * 0.92

    = 30.76 or 31

    Needed capacity requirement is 31 customer per day.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A process currently services an average of 43 customers per day. Observations in recent weeks show that its utilization is about 90 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.