It takes the Kwinzee shipyard six months (1 month = 4 weeks) with 500 workers to build a small tanker. Material costs are $32 million and overhead costs are $2 million. Workers cost $40 per hour including benefits and work 40 hours per week. The ship sells for $75 million. What is the multifactor productivity ratio? (assuming that the output is measured by its value)

+5
Answers (1)
  1. 4 April, 15:20
    0
    1.37

    Explanation:

    Kwinzee shipyard multifactor productivity ratio

    500 workers x 40 per hour x 40 hours per week x 26 numbers of week

    = 20,800,000

    Production cost = 32,000,000

    Overhead = 2,000,000

    =20,800,000+32,000,000+2,000,000

    =54,200,000

    Sales price = 75,000,000

    Hence:

    75,000,000/54,200,000

    = 1.37

    Therefore multi-factor productivity ratio will be 1.37
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “It takes the Kwinzee shipyard six months (1 month = 4 weeks) with 500 workers to build a small tanker. Material costs are $32 million and ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.