Jaycee Auto Repair has the following budgeted costs for the next year: Time Charges Material Charges Shop employees' wages and benefits $120,000 $ - Parts manager's salary and benefits - 45,000 Office employee's salary and benefits 30,000 15,000 Other overhead 15,000 40,000 Invoice cost of parts and materials - 400,000 Total budgeted costs $165,000 $500,000 The materials loading charge is 65% and the labor charge per hour is $47. Jaycee estimates that the repairs to a Cadillac Escalade damaged in an accident will take 45 hours of labor and $3,500 in parts and materials. The total cost of the repairs is

+3
Answers (1)
  1. 7 August, 01:48
    0
    Total cost of repairs:

    Material = 3,500

    Material loading charge = 3,500 * 65% = 2,275

    Labor (45hrs * $47per hr) = 2,115

    Thus, total cost = (3500 + 2275 + 2115) = $7,890
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Jaycee Auto Repair has the following budgeted costs for the next year: Time Charges Material Charges Shop employees' wages and benefits ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers