At the beginning of the period, the Assembly Department budgeted direct labor of $110,000, direct materials of $170,000, and fixed factory overhead of $28,000 for 8,000 hours of production. The department actually completed 10,000 hours of production. What is the appropriate total budget for the department, assuming it uses flexible budgeting? Round hourly rates to two decimal places.

+5
Answers (1)
  1. 26 December, 14:42
    0
    Total cost = $385,000

    Explanation:

    Giving the following information:

    Assembly Department budgeted direct labor of $110,000, direct materials of $170,000, and fixed factory overhead of $28,000 for 8,000 hours of production.

    First, we need to calculate the unitary hourly rate for the department:

    Total cost = 110,000 + 170,000 + 28,000 = 308,000

    Hourly cost = 308,000/8,000 = $38.5

    Now, for 10,000 hours:

    Total cost = 38.5*10,000 = $385,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “At the beginning of the period, the Assembly Department budgeted direct labor of $110,000, direct materials of $170,000, and fixed factory ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.