Ask Question
20 September, 17:58

Tots Toys makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. The company has orders for 12,000 of these tricycles. Current schedules yield the following information.

Requirements Component Time Space Manufacture Production

Front 3 10 2 $8 $12

Seat/Frame 4 6 2 6 9

Rear Wheel (each) 0.5 2 0.1 1 3

Available 50,000 160,000 30,000

The company obviously does not have the resources available to manufacture everything needed for the completion of 12000 tricycles so has gathered purchase information for each component. Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 12000 fully completed tricycles at the minimum cost.

+2
Answers (1)
  1. 20 September, 20:05
    0
    LetFM = number of fronts madeSM = number of seats madeWM = number of wheels madeFP = number of fronts purchasedSP = number of seats purchasedWP = number of wheels purchasedMin8FM + 6SM + 1WM + 12FP + 9SP + 3WPs. t. 3FM + 4SM +.5WM  5000010FM + 6SM + 2WM  1600002FM + 2SM +.1WM  30000FM + FP  12000SM + SP  12000WM + WP  24000FM, SM, WM, FP, SP, WP  0
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Tots Toys makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers