The functional manager is planning the billing system replacement project with the newest project manager at the company. In discussing this project, the functional manager focuses on the cost associated with running the system after it is created and the number of years the system will last before it must be replaced. What best describes what the functional manager is focusing on? (A) Project life cycle
(B) Product life cycle
(C) Project management life cycle
(D) Program management life cycle
+1
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The functional manager is planning the billing system replacement project with the newest project manager at the company. In discussing ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.