Ask Question
8 January, 07:05

On April 1, 2014, Headland Inc. entered into a cost-plus-fixed-fee contract to construct an electric generator for Altom Corporation. At the contract date, Headland estimated that it would take 2 years to complete the project at a cost of $1,962,000. The fixed fee stipulated in the contract is $467,000. Headland appropriately accounts for this contract under the percentage-of-completion method. During 2020, Headland incurred costs of $829,900 related to the project. The estimated cost at December 31, 2020, to complete the contract is $1,100,100. Altom was billed $566,000 under the contract.

Prepare a schedule to compute the amount of gross profit to be recognized by Headland under the contract for the year ended December 31, 2014.

+5
Answers (1)
  1. 8 January, 07:43
    0
    Gross profit to be recognized = $196,140

    Explanation:

    Headland Inc.

    Gross profit to be recognized by Headland at December 31, 2014 ending

    Estimated contract cost $1,962,000

    Fixed fee $467,000

    Total $1,962,000 + $467,000) $2,429,000

    Total estimated cost $1,962,000

    Gross profit ($2,429,000 - $1,962,000) $467,000

    percentage of completion: ($829,900/1,962,000) 42%

    Gross profit to be recognized: $467,000*42% $196,140
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “On April 1, 2014, Headland Inc. entered into a cost-plus-fixed-fee contract to construct an electric generator for Altom Corporation. At ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers