Sheffield Manufacturing spends 49 minutes per order on non-value-added activities. The total manufacturing cycle time is 1.8 hours. Calculate the manufacturing cycle efficiency. (Round answer to 1 decimal place, e. g. 5.1%.)

+5
Answers (1)
  1. 17 August, 21:58
    0
    The manufacturing cycle efficiency is 54.44%

    Explanation:

    Sheffield manufacturing spends 49 minutes per order

    The total manufacturing cycle rime is 1.8 hours

    Firstly we Convert 49 minutes to hours=49/60=0.82 hours, thus Sheffield manufacturing spends 49 minutes per order

    Percentage of time spent on non-value added activities = 100% - Manufacturing cycle efficiency

    (0.82/1.8) * 100 = 100%-Manufacturing cycle efficiency

    0.4555*100 = 100%-Manufacturing cycle efficiency

    45.56% = 100%-Manufacturing cycle efficiency

    Manufacturing cycle efficiency=100%-45.56% = 54.44%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Sheffield Manufacturing spends 49 minutes per order on non-value-added activities. The total manufacturing cycle time is 1.8 hours. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.