Which of the following is the correct flow of manufacturing costs? a. cost of goods sold, raw materials, work in process, finished goods b. raw materials, work in process, finished goods, cost of goods sold c. raw materials, finished goods, cost of goods sold, work in process d. work in process, finished goods, raw materials, cost of goods sold

+2
Answers (1)
  1. 18 April, 21:24
    0
    The correct answer is b. raw materials, work in process, finished goods, cost of goods sold.

    Explanation:

    The flow of manufacturing costs is the path taken by costs as they move through the process. First, costs are incurred when raw materials are purchased. Second, they move to work-in-process inventory. Once the production process is complete, the costs move to the finished goods inventory classification. When the goods are sold, the costs move to the cost of goods sold.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which of the following is the correct flow of manufacturing costs? a. cost of goods sold, raw materials, work in process, finished goods b. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers