Ask Question
21 February, 14:06

Denver company uses a job costing system. The work in process inventory on december 31 consisted of job no. 173 with a balance of $66,200. Job no. 173 has been charged with manufacturing overhead costs of $20,000. Denver allocates manufacturing overhead costs at a rate of 50% of direct labor cost. What was the amount of direct materials charged to job no. 173?

+1
Answers (1)
  1. 21 February, 15:11
    0
    Calculation of amount of direct materials charged to job no. 173:

    It is given that the work in process inventory on December 31 consisted of job no. 173 with a balance of $66,200.

    Job no. 173 has been charged with manufacturing overhead costs of $20,000. Denver allocates manufacturing overhead costs at a rate of 50% of direct labor cost. It means the direct labor cost would be 20,000/50% = $40,000

    Now we can calculate the amount of direct materials charged to job no. 173 as follows:

    Direct material Cost = Total Cost allocated to Job - Direct Labor Cost - Manufacturing Overhead Cost

    = 66200-40000-20000

    = 6200

    Hence, the amount of direct materials charged to job no. 173 is $6,200
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Denver company uses a job costing system. The work in process inventory on december 31 consisted of job no. 173 with a balance of $66,200. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers