Mondo Snow Removal's cost formula for its vehicle operating cost is $1,060 per month plus $429 per snow-day. For the month of January, the company planned for activity of 11 snow-days, but the actual level of activity was 13 snow-days. The actual vehicle operating cost for the month was $6,310. The activity variance for vehicle operating cost in January would be closest to:

+4
Answers (1)
  1. 9 October, 12:50
    0
    Activity variance = $858 unfavorable

    Explanation:

    The activity variance occurs as result of the difference between the actual level of work (activity) done and the budgeted level of work as planned.

    $

    Planned budget (1060 + (429 * 11)) = 5,779

    Flexible budget (1060 + (429 * 13) = 6,637

    Activity variance 858 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Mondo Snow Removal's cost formula for its vehicle operating cost is $1,060 per month plus $429 per snow-day. For the month of January, the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers