Standard variable overhead rate $2 per machine hour Standard fixed overhead rate $1 per machine hour Actual variable overhead costs $390,000 Actual fixed overhead costs $175,000 Budgeted fixed overhead costs $190,000 Standard machine hours per unit produced 10 Good units produced 18,000 Actual machine hours 200,000 Using the above information provided for Underfoot Products, compute the fixed overhead budget variance.

+1
Answers (1)
  1. 20 June, 19:34
    0
    Fixed overhead budget variance = $15,000 favorable

    Explanation:

    The fixed overhead budget variance is the difference between the budgeted fixed overhead expenditure and the actual fixed overhead for a given period of time.

    Where the actual amount of expenditure exceeds the budgeted it is unfavorable variance, a favorable variance implies the opposite.

    $

    Budgeted fixed overhead 190,000

    Actual fixed overhead 175,000

    Budget Variance 15,000 favorable

    Fixed overhead budget variance = $15,000 favorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Standard variable overhead rate $2 per machine hour Standard fixed overhead rate $1 per machine hour Actual variable overhead costs ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.