The following data is given for the Harry Company:

Budgeted production 26,000 units

Actual production 27,500 units

Materials:

Standard price per ounce $6.50

Standard ounces per completed unit 8

Actual ounces purchased and used in production 228,000

Actual price paid for materials $1,504,800

Labor:

Standard hourly labor rate $22 per hour

Standard hours allowed per completed unit 6.6

Actual labor hours worked 183,000

Actual total labor costs $4,020,000

Overhead:

Actual and budgeted fixed overhead $1,029,600

Standard variable overhead rate $24.50 per standard labor hour

Actual variable overhead costs $4,520,000

Overhead is applied on standard labor hours. (Round interim calculations to the nearest cent.)

The direct labor rate variance is:a. 6,000Ub. 6,000Fc. 33,000Fd. 33,000U

+5
Answers (1)
  1. 1 February, 17:03
    0
    Option (b) : $6,000 F

    Explanation:

    As per the data given in the question, computation are as follows:

    Standard rate = $22.00

    Actual labor hours = 183,000

    Actual rate = Actual labor cost : actual labor hour

    = $4,020,000 : 183,000 hours = $21.9672

    Variance = (standard rate - actual rate) * actual labor hour

    = ($22.00 - $21.9672) * 183,000

    = $6,000 F
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The following data is given for the Harry Company: Budgeted production 26,000 units Actual production 27,500 units Materials: Standard ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.