Extracts from cost information of Hebar Corp.:Simple L3 Pack Complex L7 Pack Total Setup cost allocated using direct labor-hours $19,250 $5,750 $25,000 Setup cost allocated using setup-hours $13,400 $11,600 $25,000 Assuming that setup-hours is considered a more effective cost drive for allocating setup costs than direct labor-hours.

1. Which of the following statements is true of Hebar's setup costs under traditional costing? A. L7 pack is undercosted by $5,750B. L3 pack is overcosted by $5,850C. L3 pack is undercosted by $5,850D. L7 pack is overcosted by $5,850

+2
Answers (1)
  1. Today, 18:53
    0
    The correct answer is option (B).

    Explanation:

    According to the scenario, computation of the given data are as follows:

    First we calculate for L3 pack.

    Setup cost = cost allocated using direct labor-hours - Setup cost allocated using setup-hours

    By putting the value in the formula, we get

    Setup cost = $19,250 - $13,400

    = $5,850 (Positive shows over costed)

    So, L3 pack is overcosted by $5,850
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Extracts from cost information of Hebar Corp.:Simple L3 Pack Complex L7 Pack Total Setup cost allocated using direct labor-hours $19,250 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.