The Armstrong Corporation developed a flexible budget for its production process. Armstrong budgeted to use 12,000 pounds of direct material with a standard cost of $14 per pound to produce 14,000 units of finished product. Armstrong actually purchased 24,000 pounds and used 15,000 pounds of direct material with a cost of $30 per pound to produce 14,000 units of finished product. Given these results, what is Armstrong's direct material quantity variance?

+1
Answers (1)
  1. 31 March, 20:04
    0
    Direct material quantity variance = $41,440 unfavorable

    Explanation:

    Giving the following information:

    Standard quantity per unit = 12,000/14,000 = 0.86 pounds per unit

    Standard cost of $14 per pound.

    Used 15,000 pounds of direct material with a cost of $30 per pound to produce 14,000 units of finished product.

    To calculate the direct material quantity variance, we need to use the following formula:

    Direct material quantity variance = (standard quantity - actual quantity) * standard price

    Direct material quantity variance = (0.86*14,000 - 15,000) * 14

    Direct material quantity variance = $41,440 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The Armstrong Corporation developed a flexible budget for its production process. Armstrong budgeted to use 12,000 pounds of direct ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.