Andover Systems has a standard variable overhead rate of $5.60 per machine hour, and each unit produced has a standard time allowed of 2.50 hours. The company's static budget was based on 46,000 units. Actual results for the year follow.
Actual units produced: 47,000
Actual machine hours worked: 110,000
Actual variable overhead incurred: $590,000
Andover's variable-overhead efficiency variance is:
+1
Answers (2)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Andover Systems has a standard variable overhead rate of $5.60 per machine hour, and each unit produced has a standard time allowed of 2.50 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Home » Business » Andover Systems has a standard variable overhead rate of $5.60 per machine hour, and each unit produced has a standard time allowed of 2.50 hours. The company's static budget was based on 46,000 units. Actual results for the year follow.