Consider two projects that have the same activities and the same dependencies. In the first project, the activity times are expected outcomes. The actual times will vary. In the second project, the activity times are always as expected. Assuming the expected activity times are identical across the two projects, which project will be completed first?
a. the first
b. the second
c. cannot be determined
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Consider two projects that have the same activities and the same dependencies. In the first project, the activity times are expected ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.