Jane is manager of the gbb project for her company. a vendor has offered her project a 10 percent discount if her company will order 100 units for the project. it's possible that the gbb project may need them, but their cost may be an issue. jane documents the offer and tells the vendor she'll keep the offer in mind and continue with the project as planned. what risk response has been given in this project?

+1
Answers (1)
  1. 19 April, 12:27
    0
    I guess the correct answer is Acceptance.

    Jane is manager of the GBB project for her company. A vendor has offered her a product with 10 percent discount if a company will order 100 units for the product. It's possible that the GBB project may need them, but their cost may be an issue. Jane documents the offer and tells the vendor she'll keep the offer in mind and continue with the project as planned.

    The risk response has been given in this project is Acceptance.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Jane is manager of the gbb project for her company. a vendor has offered her project a 10 percent discount if her company will order 100 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers