A financial services firm routinely processes a large volume of account change requests. a lean six sigma team wants to understand the resources required to maintain a maximum target cycle time of 16 hours. when demand fluctuates, personnel can be reassigned temporarily to increase the rate of processing. if the normal processing rate is 2 per minute, what should the maximum items in process (queue) before reassigning resources?

+3
Answers (1)
  1. 23 September, 06:40
    0
    The answer is "1920".

    This is how we calculate this;

    time = 16 hours

    normal processing rate = 2 per minute

    so,

    Things-in-Process (Queue) = 16 hours x (2 Items/Minute x 60 Minutes)

    = 1920
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A financial services firm routinely processes a large volume of account change requests. a lean six sigma team wants to understand the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers