New Company has the following information available for variable overhead costs. Direct labor hours are the cost driver for variable overhead costs. Actual variable overhead costs $3,500 Standard variable overhead costs $1.50 per hour Actual direct labor hours 2,500 hours Standard direct labor hours per unit 5 hours Units produced 500 What is the variable overhead spending variance?

+5
Answers (1)
  1. 28 May, 13:21
    0
    Variable overhead spending variance is $250 favorable.

    Explanation:

    Variable overhead spending variance

    SR = Standrad variable overhead cost = $1.50

    AR = Actual variable overhead cost = $3,500

    AH = Actual Hours work = 2,500 hours

    = (SR*AH) - AR

    = (1.50*2,500) - 3,500

    =3,750 - 3,500

    =$250 favorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “New Company has the following information available for variable overhead costs. Direct labor hours are the cost driver for variable ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers