Ask Question
30 May, 10:00

Faiza hired Bril Builders Inc. to construct her house. They signed a contract that stated Bril Builders would complete the work in 10 months, and Faiza would pay them in full. If Bril Builders completes the work but misses the date, Faiza has the right to deny the company any payment.

TRUE OR FALSE

+1
Answers (1)
  1. 30 May, 13:47
    0
    FALSE

    Explanation:

    Faiza does not hav the right to deny the company any payment even though Bril Builders Inc did not complete the work in the agreed time. Not finishing the work on the agreed time might be as a result of some factors beyond their control. Faiza must consider all these before thinking of denying them payment.

    The denial of payment would have been right if they did not complete the work or if the work done was not what they asked for or not done well.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Faiza hired Bril Builders Inc. to construct her house. They signed a contract that stated Bril Builders would complete the work in 10 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers