Gepp Manufacturing Company produces a single product. The following data apply to the standard cost of materials and labor associated with making the product: Materials quantity per unit 1 pound Materials price $ 12.50 per pound Labor quantity per unit 2 hours Labor price $ 22.50 per hour During the year, the company made 1,800 units of product. At the end of the year, the following variances had been calculated. Materials usage variance $ 1,000 Favorable Materials price variance $ 860 Unfavorable Labor usage variance $ 4,500 Unfavorable Labor price variance $ 7,125 Favorable Required Determine the actual amount of materials used. Determine the actual price paid per pound for materials. (Round your answer to 2 decimal places.) Determine the actual labor hours used. Determine the actual labor price per hour. (Round your answer to 2 decimal places.)

+4
Answers (1)
  1. 9 September, 08:42
    0
    Actual amount of material used = 1,720 pounds

    Actual price paid per pound of material = $13

    Actaul labour hours used = 2000hours

    Actual labour price per hour = $18.94

    Explanation:

    Actual amount of material used will calculated using

    material usage variance = (standard quantity - actual quantity) * standard price

    $1000 = (1800 - AQ) * $12.50

    1,000 = 22,500 - 12.50AQ

    1,000 - 22,500 = - 12.50AQ

    - 21,500 = - 12.50AQ

    AQ = - 21500/-12.50 = 1,720

    Note: Standard quantity = Actual production unit * standard quntity per unit

    = 1,800 * 1 = 1,800 pounds

    Actual price paid per unit of material

    Material price variance = (standard price - Actual price) * actual quantity

    -860 = ($12.50 - AP) 1,720

    -860 = 21500 - 1720AP

    -860 - 21500 = - 1720AP

    -22,360 = - 1720AP

    AP = - 22,360/-1720 = $13

    Actual Labour hour used

    Labour hours usages variance = (standard hour - actual hours) * standard rate per hour

    -4500 = (1800 - AH) 22.50

    -4500 = 40500 - 22.50AH

    -4500 - 40500 = - 22.50AH

    -45,000 = - 22.50AH

    AH = - 45,000/-22.50

    AH = 2000 hours

    Actual labour price per hour

    labour rate varaince = standard price - actual price) * actual quantuty

    7125 = (22.50 - AP) * 2000

    7125 = 45,000 - 2000AP

    7125 - 45,000 = - 2000AP

    -37875 = - 2000AP

    AP = - 37875/-2000

    AP = 18.9375 = 18.94
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Gepp Manufacturing Company produces a single product. The following data apply to the standard cost of materials and labor associated with ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers