All of the purchased raw material was transferred to work in process, and the materials quantity variance was unfavorable by $11,000. Direct labor - actual cost $140,000 Direct labor - standard cost for output 132,000 The labor efficiency variance was favorable by $7,600.

(a) Calculate materials price variance.

(b) Calculate materials quantity variance.

+2
Answers (1)
  1. 25 June, 15:24
    0
    Materials price variance = $8,000

    Materials quantity variance = - $11,000

    Explanation:

    (a) Calculate materials price variance

    We were given:

    Direct labor - actual cost $140,000 Direct labor - standard cost for output 132,000

    The formula for material price variance = Actual cost - Standard cost

    Material price variance = $140,000 - $132,000

    Material price variance = $8,000

    b) Material Quantity variance:

    In the question we were told that, the materials quantity variance was unfavorable by $11,000,

    Hence the Material Quantity variance because is was unfavorable is - $11,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “All of the purchased raw material was transferred to work in process, and the materials quantity variance was unfavorable by $11,000. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.